Minutes from August 1999 EXES Meeting

Link to the glossary


John, Dan, Mary Kay, and Matt attending

Electronic and Software:
The design of the header board and TEXES cables is complete. Dan needs to know when the detector will arrive. Wallace has shipped hardware. Everything should work except ethernet card. The software to be provided will include EPROMs with variety of clocking patterns. Wallace needs to communicate with Raytheon about detector clocking patterns.
Matt is compiling a list of minimum software required for winter observing run.

EPO:
We are recruiting new teachers. Mary Kay will make specific attempt to recruit from AISD.
We have gotten money (~$300) from NASA for 2 teachers. Haven't heard on one request.
Meeting dates for Fall are Sept 18, Oct 16, and Nov 20.

Optics:
CO2 laser tests of 36 inch grating inside TEXES going well. More tests coming.

Dewar Design:
Design is progressing slowly. John expects design could be done in 2 months. John wants to know the level of design required for FAA Critical Airworthiness Design Review. John is concerned that Jeff Cottrell (McDonald draftsman) may be leaving before design is entered into mechanical desktop.

Action Items:
Mary Kay:

  • contact AISD to recruit teachers

    Matt:

  • circulate minimum software list
  • contact FAA IPT for CADR requirements

    John:

  • contact Raytheon about chip delivery
  • circulate dewar design drawings for comment